Meeting Name: Facilities Committee Agenda status: Final
Meeting date/time: 12/8/2009 5:00 PM Minutes status: Final  
Meeting location: Board Room, Paul Robeson Building, 1025 2nd Avenue, Oakland, CA 94606-2212
Published agenda: Agenda Agenda Published minutes: Minutes Minutes  
Meeting video: eComment: Not available  
Attachments:
File #Ver.Agenda #NameTypeTitleActionResultAction DetailsVideo
09-3334 1 Minutes - Facilities Committee - November 10, 2009Minutes, CommitteeApproval by Facilities Committee of its Minutes of November 10, 2009.AdoptedPass Action details Video Video
09-2822 1 Professional Services Agreement - Simplex Grinnell - District-wide Fire Alarm Repair Project Agreement or ContractApproval by the Board of Education of Professional Services Agreement between District and Simplex Grinnell, Livermore, CA, for the latter to provide Fire Alarm repairs and supplementing of District's fire alarm maintenance technicians in maintaining the District's fire alarm system and various other items described herein in conjunction with the District-wide Fire Alarm Repair Project, for the period commencing January 1, 2010 and concluding no later than January 1, 2011, in an amount not to exceed $750,000.00.Recommended FavorablyPass Action details Not available
09-2874 1 Amendment No. 1 - AGS, Inc. - Urban Promise Academy Multi-Purpose Building Project Agreement or ContractApproval by the Board of Education of Amendment No. 1 to Professional Services Agreement between District and AGS, Inc., San Francisco, CA, for the latter to provide additional services, which include project consultation; pre-grading meeting for mass grading; periodic observation during mass grading; observation of utility trench backfill and various other items described herein in conjunction with the Urban Promise Academy Multi-Purpose Building Project, in an additional amount not to exceed $14,955.00, increasing the Agreement from $12,973.73 to a not-to-exceed amount of $27,928.73. All other terms and conditions of the Agreement remain in full force and effect.Recommended FavorablyPass Action details Not available
09-2903 1 Amendment No. 3 - VBN - Carter Middle School Modernization Project Agreement or ContractApproval by the Board of Education of Amendment No. 3 to Professional Services Agreement between District and VBN, Oakland, CA, for District to provide the latter reimbursement of Division of State Architect (DSA) document retrieval fees and Ford Graphics reproduction fees in conjunction with the Carter Middle School Modernization Project, in an additional amount not to exceed $569.43, increasing the Agreement from $263,295.00 to a not-to-exceed amount of $263,864.43, and extending the end date from December 31, 2008 to December 31, 2009. All other terms and conditions of the Agreement remain in full force and effect.Recommended FavorablyPass Action details Not available
09-2908 1 Amendment No. 3 - Inspection Services, Inc. - Chabot Elementary School Portable Classroom Replacement ProjectAgreement or ContractApproval by the Board of Education of Amendment No. 3 to Professional Services Agreement between District and Inspection Services, Inc., Berkeley, CA, for the latter to provide additional special inspection and material testing services as required for new structures in conjunction with the Chabot Elementary School Portable Classroom Replacement Project, in an additional amount not to exceed $30,176.93, increasing the Agreement from $76,500.00 to a not-to-exceed amount of $106,676.93, and extending the end date from December 31, 2009 to June 30, 2010. All other terms and conditions of the Agreement remain in full force and effect.Recommended FavorablyPass Action details Not available
09-3104 1 Grant Agreement Between Oakland Unified School District and the City of Oakland - McClymonds Youth and Family CenterAgreement or ContractApproval by the Board of Education of Resolution No. 0910-0097 - Approving Grant Agreement between the District and the City of Oakland, for the Development and Construction of the McClymonds Youth and Family Center.Recommended FavorablyPass Action details Not available
09-3143 1 Amendment No. 1 - Testing Engineers - Stonehurst Small Schools Conversion Project Agreement or ContractApproval by the Board of Education of Amendment No. 1 to Professional Services Agreement between District and Testing Engineers, San Leandro, CA, for the latter to provide additional soil and concrete inspections that were required by Division of State Architect (DSA), but not included in the original scope of work in conjunction with the Stonehurst Small Schools Conversion Project, in an additional amount not to exceed $2,272.00, increasing the Agreement from $4,822.00 to a not-to-exceed amount of $7,094.00, and extending the end date from July 1, 2009 to December 31, 2009. All other terms and conditions of the Agreement remain in full force and effect.Recommended FavorablyPass Action details Not available
09-3191 1 Project Budget Increase - Various District Wide Play Structure Repairs ProjectAppropriationApproval by the Board of Education of Resolution No. 0910-0102 - Authorizing and approving the Project Budget Increase for the Various District Wide Play Structure Repairs Project, in the amount of $1,500,000.00, increasing the project budget from $100,000.00 to $1,600,000.00.Recommended FavorablyPass Action details Not available
09-3197 1 Professional Services Agreement - First Alarm Security and Patrol - Chabot Elementary School Portable Classroom Replacement Project Agreement or ContractApproval by the Board of Education of Professional Services Agreement between District and First Alarm Security and Patrol, Aptos, CA, for the latter to provide security at Chabot Elementary School to protect the school from vandalism and intrusion alarm malfunctions in conjunction with the Chabot Elementary School Portable Classroom Replacement Project, for the period commencing September 4, 2009 and concluding no later than September 10, 2009, in an amount not to exceed $3,052.00.Recommended FavorablyPass Action details Not available
09-3198 1 Professional Services Agreement - HY Architects, Inc. - Stonehurst Child Development Center (CDC) Project Agreement or ContractApproval by the Board of Education of Professional Services Agreement between District and HY Architects, Inc., Oakland, CA, for the latter to provide design services for the Stonehurst CDC Replacement project; building design is to include a complete renovation to the existing new CDC building of approximately 6,700 square feet with 3-4 classrooms spaces, restrooms, custodial space, and office/administration space; scope will include site improvements necessary to support the new building; project is to be designed to achieve CHPS certification and this contract includes $33,000.00 for CHPS processing and documentation. Scope also includes 3rd party estimates during the design phase; project also includes interim housing portables during the construction of the new building; includes $10,000.00 for reimbursable expenses in conjunction with the Stonehurst Child Development Center (CDC) Project, for the period commencing December 17, 2009 and concluding upon completion of the desired services described herein, but no later than December 31, 2011, in an amount not to exceed $442,000.00.Recommended FavorablyPass Action details Not available
09-3199 1 Professional Services Agreement - Loving and Campos Architects, Inc. (LCA - Laurel Child Development Center (CDC) Project Agreement or ContractApproval by the Board of Education of Professional Services Agreement between District and Loving and Campos Architects, Inc. (LCA), Oakland, CA, for the latter to provide design services for the Laurel CDC Replacement project; building design is to include a complete renovation to the existing new CDC building; building will be approximately 6,500 square feet with 3-4 classrooms spaces, restrooms, custodial space, and office/administration space; scope will include site improvements necessary to support the new building. Project is to be designed to achieve CHPS certification and this contract includes $15,000.00 for CHPS processing and documentation; scope also includes 3rd party estimates during the design phase. Project also includes interim housing portables during the construction of the new building; contract includes $30,000.00 for reimbursable expenses, in conjunction with the Laurel Child Development Center (CDC) Project, for the period commencing December 17, 2009 and concluding upon completion of the desired services described herein, but no later than December 31, 2011, in an amount not to exceed $333,000.00.Recommended FavorablyPass Action details Not available
09-3200 1 Professional Services Agreement - Michael Willis Architects, Inc. - Thurgood Marshall Elementary School Roof Replacement Project Agreement or ContractApproval by the Board of Education of Professional Services Agreement between District and Michael Willis Architects, Inc., Oakland, CA, for the latter to provide written specifications and drawings sufficient to solicit bids for roof replacement and various other items described herein, in conjunction with the Thurgood Marshall Elementary School Project, for the period commencing November 19, 2009 and concluding no later than June 30, 2010, in an amount not to exceed $34,200.00.Recommended FavorablyPass Action details Not available
09-3201 1 Professional Services Agreement - Oakley and Oakley Architects - Hintil KUU Child Development Center (CDC) Project Agreement or ContractApproval by the Board of Education of Professional Services Agreement between District and Oakley and Oakley Architects, Oakland, CA, for the latter to provide design services for the Hintil KUU CDC Replacement project: building design is to include a complete renovation to the existing new CDC building; building will be approximately 6,000 square feet with 3-4 classrooms spaces, restrooms, custodial space, and office/administration space; scope will include site improvements necessary to support the new building; project is to be designed to achieve CHPS certification and this contract includes CHPS processing and documentation; scope also includes 3rd party estimates during the design phase. Project also includes interim housing portables during the construction of the new building; contract includes $10,000.00 for reimbursable expenses, in conjunction with the Hintil KUU Child Development Center (CDC) Project, for the period commencing December 17, 2009 and concluding upon completion of the desired services described herein, but no later than December 31, 2011, in an amount not to exceed $336,500.00.Recommended FavorablyPass Action details Not available
09-3202 1 Memorandum of Understanding - Elder Care Alliance - Oakland Adult and Career EducationAgreement or ContractApproval by the Board of Education of Memorandum of Understanding between District and Elder Care Alliance, Oakland CA, for the provision of Adult and Career Education classes on the latter's owned premises at 3134 Foothill Blvd., Oaskland, CA, and 2361 E. 29th Street., Oakland, CA, respectively, pursuant to the terms and conditions stated in said MOU, for the period of December 16th 2009 through June 30, 2012, at no cost to the District.Recommended FavorablyPass Action details Not available
09-3258 1 Project Budget, Key Code and Project Number - Claremont Landscaping ProjectResolutionApproval by the Board of Education of Resolution No. 0910-0104 - Authorizing and approving the New Project Budget, Key Code and Project Number for Claremont Landscaping Project in the amount of $800,000.00.Recommended FavorablyPass Action details Not available
09-3260 1 Change Order No. 4 - Albay Construction Co. - Madison Middle School Modernization Project Agreement or ContractApproval by the Board of Education of Change Order No. 4 to Construction Contract between District and Albay Construction Co., Martinez, CA, for the latter to repair vandalized conduits at the gym roof, supply and install thresholds, repair two bent covered walkway posts, make modifications to allow the installation of J-1 light fixtures, add eleven (11) thresholds to correct existing conditions and various other items described herein, in conjunction with the Madison Middle School Modernization Project, in the additional amount of $90,526.32, increasing the Agreement from $6,186,618.81 to $6,277,145.13. All other terms and conditions of the Agreement remain in full force and effect. Recommended FavorablyPass Action details Not available
09-3261 1 Change Order No. 4 - Albay Construction Co. - Havenscourt Middle School Modernization Project Agreement or ContractApproval by the Board of Education of Change Order No. 4 to Construction Contract between District and Albay Construction Co., Martinez, CA, for the latter to delete one row from gym bleachers, substitute ceramic tile over existing concrete slab, convert rooms in the Family Resource Center and various other items described herein in conjunction with the Havenscourt Middle School Modernization Project, in the additional amount of $67,209.00, increasing the Agreement from $1,922,072.91 to $1,989,281.91. All other terms and conditions of the Agreement remain in full force and effect. Recommended FavorablyPass Action details Not available
09-3262 1 Change Order No. 1 - Brayer Electric Company - Highland Elementary School Fire Alarm Upgrade Project Agreement or ContractApproval by the Board of Education of Change Order No. 1 to Construction Contract between District and Brayer Electric Company, San Leandro, CA, for the latter to refund unused allowance balancing contract, in conjunction with the Highland Elementary School Fire Alarm Upgrade Project, in the amount of ($2,162.00), decreasing the Agreement from $199,700.00 to $197,538.00. All other terms and conditions of the Agreement remain in full force and effect. Recommended FavorablyPass Action details Not available
09-3263 1 Change Order No. 5 - Cal Pacific Construction - Lincoln Elementary School Classroom Replacement Project Agreement or ContractApproval by the Board of Education of Change Order No. 5 to Construction Contract beween District and Cal Pacific Construction, Pacifica, CA, for the latter's returned hardware submittal, HVAC headout, deletion and addition of light fixtures, HVAC curbs, transition point at entry doors and various other items described herein, in conjunction with the Lincoln Elementary School Classroom Replacement Project, in the additional amount of $13,818.67, increasing the Agreement from $6,495,921.74 to $6,509,740.41. All other terms and conditions of the Agreement remain in full force and effect. Recommended FavorablyPass Action details Not available
09-3264 1 Change Order No. 6 - Cal Pacific Construction - Lincoln Elementary School Classroom Replacement Project Agreement or ContractApproval by the Board of Education of Change Order No. 6 to Construction Contract between District and Cal Pacific Construction, Pacifica, CA, for the latter to change vinyl coated fencing to galvanized fencing, correct elevator deficiencies, in conjunction with the Lincoln Elementary School Classroom Replacement Project in the amount of ($6,733.42), decreasing the Agreement from $6,509,740.41 to $6,503,006.99. All other terms and conditions of the Agreement remain in full force and effect. Recommended FavorablyPass Action details Not available
09-3266 1 Change Order No. 2 - Duran & Venables, Inc. - Thornhill Elementary School Paving Project Replacement Project Agreement or ContractApproval by the Board of Education of Change Order No. 2 to Construction Contract between District and Duran & Venables, Inc., Milipitas, CA, for the latter credits and extras for additional work required (concrete cap existing gas line, new concrete driveway, rebar, etc.) and credits for (herbicide, topography survey, prime coating) and various other items described herein, in conjunction with the Thornhill Elementary School Paving Project, in the amount of ($3,256.00), decreasing the Agreement from $474,711.00 to $471,455.00. All other terms and conditions of the Agreement remain in full force and effectRecommended FavorablyPass Action details Not available
09-3267 1 Change Order No. 4 - J. W. & Sons, Inc. - Castlemont High School Auditorium Renovations Project Agreement or ContractApproval by the Board of Education of Change Order No. 4 to Construction Contract between District and J. W. & Sons, Inc., Petaluma, CA, for the latter per ASI #05 - to remove and re-install conduit and wire for the Fire Alarm and Security devices in the lobby area above the new ceiling, per ASI #51, change lobby buildings signage from stainless steel lettering to bronze lettering, add eight 4" bronze letters and various other items described herein, in conjunction with the Castlemont High School Auditorium Renovations Project, in the additional amount of $118,895.00, increasing the Agreement from $3,033,028.00 to $3,151,923.00. All other terms and conditions of the Agreement remain in full force and effect. Recommended FavorablyPass Action details Not available
09-3273 1 Professional Services Agreement - ACC Environmental - Oakland High School Modernization Project Agreement or ContractApproval by the Board of Education of Professional Services Agreement between District and ACC Environmental, Oakland, CA, for the latter to provide Soil Sampling, for off-site disposal, as required by the waste receiver and for Indoor Air-Quality Sampling; as per the request and subsequent directive by Assistant Superintendent for Facilities, as indicated in the attached proposal incorporated into the contract to the extent that it is subordinate to and not inconsistent with the contract terms, in conjunction with the Oakland High School Modernization Project, for the period commencing December 17, 2009 and concluding no later than June 30, 2011, in an amount not to exceed $26,305.25.Recommended FavorablyPass Action details Not available
09-3274 1 Professional Services Agreement - AGS, Inc. - Urban Promise Academy Multi-Purpose Building Project Agreement or ContractApproval by the Board of Education of Professional Services Agreement between District and AGS, Inc., San Francisco, CA, for the latter to resolve Division of State Architect (DSA) comments on the Final Report - Geotechnical and Geologic/Seismic Hazardous Study and resolve comments/concerns from the California Department of Conservation and an unpaid amount on a Purchase Order not paid previously in the amount of $713.73, in conjunction with the Urban Promise Academy Multi-Purpose Building Project, for the period commencing December 17, 2009 and concluding no later than February 28, 2010, in an amount not to exceed $12,973.73.Recommended FavorablyPass Action details Not available
09-3275 1 Professional Services Agreement - Golden Associates Landscape - Claremont Middle School Landscaping Project Agreement or ContractApproval by the Board of Education of Professional Services Agreement between District and Golden Associates Landscape, Oakland, CA, for the latter to provide new irrigation throughout, new parking lot, new multi-use grass area with track, new grass area with basketball court, upgrade existing community garden, upgrade existing interior and exterior courtyard, new greenhouse and miscellaneous planting throughout the site, in conjunction with the Claremont Middle School Landscaping Project, for the period commencing December 17, 2009 and concluding no later than December 17, 2010, in an amount not to exceed $41,019.00.Recommended FavorablyPass Action details Not available
09-3276 1 Purchase and Delivery Contract - Modular Space - Joaquin Miller Elementary School Portable Replacement Project Agreement or ContractApproval by the Board of Education of Purchase and Delivery Contract between District and Modular Space, Hayward, CA, for the latter to purchase two (2) portables as described in agreement located on site, in conjunction with the Joaquin Miller Elementary School Portable Replacement Project for the period commencing November 19, 2009 and terminating December 31, 2009, in an amount not to exceed $28,476.00.Recommended FavorablyPass Action details Not available
09-3278 1 Professional Services Agreement - Roland Lakes - District-wide Cost Estimating and Related Services Project Agreement or ContractApproval by the Board of Education of a Professional Services Agreement between District and Roland Lakes, Oakland, CA, for the latter to provide professional cost estimating and related services, including but not limited to providing cost estimates for new, and modernization projects, proposed change orders and related services as needed, in conjunction with the District-wide Cost Estimating and Related Services Project, for the period commencing January 1, 2010 and concluding no later than December 31, 2010, in an amount not to exceed $120,000.00.Recommended FavorablyPass Action details Not available
09-3279 1 Professional Services Agreement - S. Meek Architecture - Havenscourt Middle School New Classroom and Cafeteria Building Project Agreement or ContractApproval by the Board of Education of Professional Services Agreement between District and S. Meek Architecture, San Francisco, CA, for the latter to provide design and construction administration services which include schematic design, design development, preparation of construction documents, bidding and agency approval, construction administration and close out for both phases of the project, in conjunction with the Havenscourt Middle School New Classroom and Cafeteria Building Project, for the period commencing December 17, 2009 and concluding upon completion of the desired services described herein, but no later than June 30, 2013, in an amount not to exceed $969,000.00.Recommended FavorablyPass Action details Not available
09-3281 1 Amendment No. 2 - Consolidated Engineering Laboratories - Lincoln Elementary School New Classroom Building Project Agreement or ContractApproval by the Board of Education of Amendment No. 2 to Professional Services Agreement between District and Consolidated Engineering Laboratories, San Ramon, CA, for the latter to provide additional inspection for unanticipated field welding that occurred for the new Classroom Building, due to an unforeseen condition, whereas Division of State Architect (DSA) requires independent testing and inspection with in-house review and CBC requirements in conjunction with the Lincoln Elementary School New Classroom Building Project, in an amount not to exceed $1,457.41, increasing the Agreement from $61,816.04 to a not-to-exceed amount of $63,273.45. All other terms and conditions of the Agreement remain in full force and effect.Recommended FavorablyPass Action details Not available
09-3282 1 Amendment No. 4 - Ninyo and Moore - Downtown Education Complex Project Agreement or ContractApproval by the Board of Education of Amendment No. 4 to Professional Services Agreement between District and Ninyo and Moore, Oakland, CA, for the latter to provide additional abatement monitoring and demolition oversight for Portables 3, 13, 14, 15, 16 and 18, due to a District requested change, per the attached agreement which is subordinate to and not inconsistent with the terms and conditions of the agreement in conjunction with the Downtown Education Complex Project in an additional amount not to exceed $24,300.00, increasing the Agreement from $16,600.00 to a not-to-exceed amount of $40,900.00, and extending the end date from December 31, 2009 to May 1, 2010. All other terms and conditions of the Agreement remain in full force and effect.Recommended FavorablyPass Action details Not available
09-3283 1 Amendment No. 1 - Waste Management of Alameda County - Oakland High School Modernization Project Agreement or ContractApproval by the Board of Education of Amendment No. 1 to Professional Services Agreement between District and Waste Management of Alameda County, Oakland, CA, for the latter to provide additional roll-bin service to school site for clearance by teachers, staff for moving/Modernization needs, in conjunction with the Oakland High School Modernization Project, in an amount not to exceed $2,051.52, increasing the Agreement from $9,000.00 to a not-to-exceed amount of $11,051.52. All other terms and conditions of the Agreement remain in full force and effect.Recommended FavorablyPass Action details Not available
09-3298 1 Professional Services - Dougherty and Dougherty Architects LLP - Arroyo Viejo CDC Replacement ProjectAgreement or ContractApproval by the Board of Education of Professional Services Contract between District and Dougherty and Dougherty Architects LLP, Oakland, CA, for the latter to provide design and construction administration, schematic design, design development, preparation of construction documents and bidding and agency approval, in conjunction with the Arroyo Viejo CDC Replacement Project, for the period commencing December 17, 2009 and concluding upon completion of the desired services described herein, but no later than December 17, 2011, in an amount not to exceed $342,000.00.Recommended FavorablyPass Action details Not available
09-3305 1 Grant Acceptance - Air Resources Board - Caldecott Tunnel Project Impact - Chabot Elementary School and the Claremont Middle SchoolAgreement or ContractApproval by the Board of Education of Grant Agreement between District and Air Resources Board, accepting funding from the latter for the Caldecott Tunnel Project, as specified in the Statement of Work, incorporated herein by reference as though fully set forth, at the Chabot Elementary School and the Claremont Middle School, in the amount of $2,000,000.00, for the period July 1, 2009 through June 30, 2012, pursuant to terms and conditions there of, if any.Recommended FavorablyPass Action details Not available
09-3308 1 Professional Services Contract - Vista Environmental Consulting, LLC Agreement or ContractApproval by the Board of Education of a Professional Services Contract between the District and Vista Environmental Consulting, LLC., Oakland, CA, for the latter to clean-up/container, characterize, transport and properly dispose of Hazardous Waste, at the Corporate Facilities Yard, for the period of November 23, 2009 through June 30, 2010, at a cost not to exceed $25,734.00.Recommended FavorablyPass Action details Not available
09-3311 1 Amendment No. 1 - Dougherty & Dougherty Architects - Montclair Elementary School Interim Housing Project Agreement or ContractApproval by the Board of Education of Amendment No. 1 to Professional Services Agreement between District and Dougherty & Dougherty Architects, Oakland, CA, for the latter to provide additional services to complete the contracted services, which include, added survey for portables, a City required fire hydrant pressure verification and the alarm system change from a stand-alone system to an integrated system to meet revised District standards, due to a District request, in conjunction with the Montclair Elementary School Interim Housing Project, in an additional amount not to exceed $12,211.19, increasing the Agreement from 46,500.00 to a not-to-exceed amount of $58,711.19, and extending the end date from December 31, 2009 to March 31, 2010. All other terms and conditions of the Agreement remain in full force and effect.Recommended FavorablyPass Action details Not available
09-3325 1 Facility Use Agreement Between Oakland Unified School District and the Oakland Military Institute College Prep AcademyAgreement or ContractApproval by the Board of Education of the Resolution No. 0910-0106 Facility Use Agreement between District and Oakland Military Institute College Preparatory Academy (OMI), giving consent to OMI to submit an application to the Office of Public School construction for a preliminary apportionment for rehabilitation funds for use at the Longfellow Elementary School campus.Recommended FavorablyPass Action details Not available
09-2949 1 Board Policy - Business Services and Non-Instructional Operations - BP 3285 - Vegetation PolicyBoard PolicyApproval by the Board of Education of Board Policy - Business Services and Non-Instructional Operations - BP 3285 - Vegetation Policy.Discussed  Action details Video Video
09-3342 1 Facilities Use Agreement - Leadership Public Schools College Park Charter School - Dedicated and Shared Space - Castlemont Community of Schools Agreement or ContractApproval by the Board of Education of a Proposition 39 Charter Facilities Use Agreement between District and Leadership Public Schools, a non-profit public benefit corporation operating College Park Charter School, for the latter's use of dedicated space and shared space, within District's facility known as the Castlemont Community of Schools ("Castlemont"), located at 8601 MacArthur Boulevard, Oakland, CA 94605, as more specifically described in Exhibit C of Agreement, commencing December 16, 2009 and ending July 31, 2010, for the 2009-2010 School Year, at a pro rata shared cost not to exceed $144,983.28.Recommended FavorablyPass Roll call Video Video
09-3343 1 Facilities Use Agreement - Bay Area Technology School - Portion of Carter School SiteAgreement or ContractApproval by the Board of Education of a Proposition 39 Charter Facilities Use Agreement between District and Bay Area Technology School, a Charter School, for the latter's use of a portion of the public site within District known as the Verdese Carter Middle School site ("Carter"), located at 4521 Webster Street, Oakland, CA 94608, sharing the site with Oakland International High School, as more specifically described in Exhibit C of Agreement, commencing December 16, 2009 and ending July 31, 2010, for the 2009-2010 School Year, at a pro rata shared cost not to exceed $54,207.84.Recommended FavorablyPass Action details Video Video
09-3344 1 Facilities Use Agreement - Bay Area Technology School - Portable on Carter School SiteAgreement or ContractApproval by the Board of Education of Proposition a 39 Charter Facilities Use Agreement By and Between District and Bay Area Technology School, a Charter School, for the latter's use of a portable on the public site within District known as the Verdese Carter Middle School site ("Carter"), located at 4521 Webster Street, Oakland, CA 94608, a shared site with Oakland International High School, as more specifically described in Exhibit A of Agreement, commencing December 16, 2009 and ending July 31, 2010, for the 2009-2010 School Year, at an annual Contract Fee, for ten months, not to exceed $10,000.00 and for other costs specified within said Agreement.Recommended FavorablyPass Action details Video Video
09-3359 1 District's Continuing Unmet Facilities Needs Discussion ItemAdditional discussion of the District's continuing long term unmet facilities renovation, rehabilitation, new construction needs and the prospect of acquisition of additional resources - federal, state, local - to address same.Discussed  Action details Video Video