File #: 24-2414    Version: 1 Name: Change Order No. 1, Agreement Between Owner and Contractor – RK Roofing & Construction, Inc. – Roosevelt Middle School Gym Replacement Project – Buildings and Grounds Department
Type: Agreement or Contract Status: Passed
File created: 9/24/2024 In control: Deputy Chief, Facilities Planning and Management
On agenda: 10/23/2024 Final action: 10/23/2024
Enactment date: 10/23/2024 Enactment #: 24-1991
Title: Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and RK Roofing & Construction, Inc., San Leandro, CA, for the latter to provide materials and installation of 20 cast iron drains, two access hatches for drains, and new plywood and waterproofing around 20 drains, for the Roosevelt Middle School Gym Replacement Project, in the amount of $110,363.01, increasing the Agreement not-to-exceed amount from $558,795.00 to $669,158.01. All other terms and conditions of the Agreement remain in full force and effect.
Attachments: 1. 24-2414 Change Order No. 1, Agreement Between Owner and Contractor – RK Roofing & Construction, Inc. – Roosevelt Middle School Gym Replacement Project – Buildings and Grounds Department
Contact: preston.thomas@ousd.org

title

Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and RK Roofing & Construction, Inc., San Leandro, CA, for the latter to provide materials and installation of 20 cast iron drains, two access hatches for drains, and new plywood and waterproofing around 20 drains, for the Roosevelt Middle School Gym Replacement Project, in the amount of $110,363.01, increasing the Agreement not-to-exceed amount from $558,795.00 to $669,158.01. All other terms and conditions of the Agreement remain in full force and effect.