File #: 24-0475    Version: 1 Name: Change Order No. 1, Agreement Between Owner and Contractor – Mar Con Builders, Inc. – Kaiser Child Development Center Site Improvements Project – Division of Facilities Planning and Management
Type: Agreement or Contract Status: Passed
File created: 2/21/2024 In control: Deputy Chief, Facilities Planning and Management
On agenda: 4/10/2024 Final action: 4/10/2024
Enactment date: 4/10/2024 Enactment #: 24-0649
Title: Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and Mar Con Builders, Inc., Oakland, CA, for the latter to perform: * PCO #12 for installation of 3 new play structures. * PCO #13 for 6" wide 24" deep concrete curb placed as a divider between pavers and existing asphalt. * PCO #14 for expansion joints needed at retaining wall. * PCO #15 for demolition of concrete apron that is not ADA compliant for the Kaiser Child Development Center Site Improvements Project, in the additional amount of $156,911.00, increasing the not to exceed amount of the Agreement from $6,551,440.00 to $6,708,351.00; and extending the term of the Agreement by an additional 239 Calendar Days, from June 8, 2023 through November 4, 2023 to June 30, 2024. All other terms and conditions of the Agreement remain in full force and effect.
Attachments: 1. 24-0475 Change Order No. 1, Agreement Between Owner and Contractor – Mar Con Builders, Inc. – Kaiser Child Development Center Site Improvements Project – Division of Facilities Planning and Management
Related files: 23-1135
Contact: Preston.Thomas@ousd.org

title

Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and Mar Con Builders, Inc., Oakland, CA, for the latter to perform:

                     PCO #12 for installation of 3 new play structures.

                     PCO #13 for 6" wide 24" deep concrete curb placed as a divider between pavers and existing asphalt.

                     PCO #14 for expansion joints needed at retaining wall.

                     PCO #15 for demolition of concrete apron that is not ADA compliant

for the Kaiser Child Development Center Site Improvements Project, in the additional amount of $156,911.00, increasing the not to exceed amount of the Agreement from $6,551,440.00 to $6,708,351.00; and extending the term of the Agreement by an additional 239 Calendar Days, from June 8, 2023 through November 4, 2023 to June 30, 2024. All other terms and conditions of the Agreement remain in full force and effect.