File #: 21-2691    Version: 1 Name: 1885Change Order No. 1, Agreement Between Owner and Contractor – Everlast Development, Inc. – Burbank Elementary School Vegetation Fire Management Project – Department of Buildings and Grounds
Type: Agreement or Contract Status: Passed
File created: 10/29/2021 In control: Deputy Chief, Facilities Planning and Management
On agenda: 12/1/2021 Final action: 12/1/2021
Enactment date: 12/1/2021 Enactment #: 21-1885
Title: Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and Everlast Development, Inc., Oakland, CA, providing credit for remaining unused Contingency Allowance for the Burbank Elementary School Vegetation Fire Management Project, as a deductive change in the amount of $550.00, reducing the Agreement price from $18,700.00 to $18,150.00, providing a time extension of 98 days, changing the Agreement term from July 26, 2021 through August 25, 2021 to December 1, 2021. All other terms and conditions of the Agreement remain in full force and effect.
Attachments: 1. 21-2691 Change Order No. 1, Agreement Between Owner and Contractor – Everlast Development, Inc. – Burbank Elementary School Vegetation Fire Management Project – Department of Buildings and Grounds
Related files: 21-1806
Contact: Tadashi.Nakadegawa@ousd.org

Title

Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and Everlast Development, Inc., Oakland, CA, providing credit for remaining unused Contingency Allowance for the Burbank  Elementary School Vegetation Fire Management Project, as a deductive change in the amount of $550.00, reducing the Agreement price from $18,700.00 to $18,150.00, providing a time extension of 98 days, changing the Agreement term from July 26, 2021 through August 25, 2021 to December 1, 2021. All other terms and conditions of the Agreement remain in full force and effect.