File #: 21-1602    Version: Name: Amendment No. 3, Lease Lease-Back- Overaa/Tulum/Eclipse, JV - Foster The Center Project - Division of Facilities Planning and Management
Type: Agreement or Contract Status: Passed
File created: 6/7/2021 In control: Deputy Chief, Facilities Planning and Management
On agenda: 9/8/2021 Final action: 9/8/2021
Enactment date: 9/8/2021 Enactment #: 21-1440
Title: Approval by the Board of Education of Amendment No. 3, Lease Leaseback by and between the District and Overaa/Tulum/Eclipse, Richmond, CA, for the latter to provide Preconstruction services performed by the General Contractor and for interest that is required for the Lease Payments but was not included in the GMP*, for the Foster the Center Project, in an additional amount of $270,031.69, and including total amount from Change Order No 5, $519,015.06, increasing contract price from $50,551,133.91 to $51,450,180.66, and authorizing the President and Secretary of the Board to sign the Amendment for same with said Contractor. All other terms and conditions of the Agreement remain in full force and effect. ___ *The Pre-Construction Services is not construction work. It is assistance with negotiating with all the impacted vendors from Phase I (which was ended by OUSD) and assisting with value-engineering before finalizing the GMP
Attachments: 1. 21-1602 Amendment No. 3, Lease Lease-Back- Overaa/Tulum/Eclipse, JV - Foster The Center Project - Division of Facilities Planning and Management
Related files: 17-1825, 18-0089, 18-2166
Contact: Tadashi.Nakadegawa@ousd.org

Title

Approval by the Board of Education of Amendment No. 3, Lease Leaseback by and between the District and Overaa/Tulum/Eclipse, Richmond, CA, for the latter to provide Preconstruction services performed by the General Contractor and for interest that is required for the Lease Payments but was not included in the GMP*, for the Foster the Center Project, in an additional amount of $270,031.69, and including total amount from Change Order No 5, $519,015.06, increasing contract price from $50,551,133.91 to $51,450,180.66, and authorizing the President and Secretary of the Board to sign the Amendment for same with said Contractor. All other terms and conditions of the Agreement remain in full force and effect.

___

 

*The Pre-Construction Services is not construction work. It is assistance with negotiating with all the impacted vendors from Phase I (which was ended by OUSD) and assisting with value-engineering before finalizing the GMP