File #: 13-2621    Version: 1 Name: Change Order No. 1 - Safeshields, Inc. - Lowell Middle School Modernization Project
Type: Agreement or Contract Status: Passed
File created: 10/31/2013 In control: Facilities Committee
On agenda: 11/20/2013 Final action: 11/20/2013
Enactment date: 11/20/2013 Enactment #: 13-2464
Title: Approval by the Board of Education of Change Order No. 1 to Construction Contract with Safeshields, Inc., Oakland, CA, for payment of additional cost of stucco patching which was more extensive than anticipated, after complete demo, in conjunction with the Lowell Middle School Modernization Project in the additional amount of $3,638.00, increasing the Agreement from $30,800.00 to $34,428.00. All other terms and conditions of the Agreement remain in full force and effect.
Attachments: 1. 13-2621 Change Order No. 1 - Safeshields, Inc. - Lowell Middle School Modernization Project
Contact: Timothy.White@ousd.k12.ca.us
Title
Approval by the Board of Education of Change Order No. 1 to Construction Contract with Safeshields, Inc., Oakland, CA, for payment of additional cost of stucco patching which was more extensive than anticipated, after complete demo, in conjunction with the Lowell Middle School Modernization Project in the additional amount of $3,638.00, increasing the Agreement from $30,800.00 to $34,428.00. All other terms and conditions of the Agreement remain in full force and effect.