Title
Approval by the Board of Education of Change Order No. 3 to Construction Contract with West Bay Builders, Inc., Novato, CA, for the latter to perform additional Scope of Work described as (99) Asi #35 - wireless hardware upgrade; (107) RFI #387 - demo (e) footing at Building B; (108) RFI #378 - re-route of (e) electrical feed to Building D and various other items described herein in conjunction with the Cox New Classroom Building Project, in the additional amount of $32,455.00, increasing the Agreement from a not to exceed amount of $11,577,923.00 to $11,610,378.00. All other terms and conditions of the Agreement remain in full force and effect.