Approval by Board of Education of Change Order No. 2 to Construction Contract with Cal Pacific Construction, Pacifica, CA, for the latter to install conduit for temporary; main breaker in MSB for Temporary Power; patch roof penetration; temporary generator rental and security and various other items as described herein in conjunction with the Lincoln Elementary School Classroom Replacement Project in the amount of $55,443.98, increasing the Agreement from $6,415,864.89 to $6,471,308.87. All other terms and conditions of the Agreement remain in full force and effect.