File #:
|
24-1726
Version:
1
|
Name:
|
Agreement Between Owner and Contractor - R. F. Contractors - Bella Vista Elementary School Cafeteria Flooring Replacement Project - Division of Buildings and Grounds
|
Type:
|
Agreement or Contract
|
Status:
|
Passed
|
On agenda:
|
8/14/2024
|
Final action:
|
8/14/2024
|
Enactment date:
|
8/14/2024
|
Enactment #:
|
24-1377
|
Title:
|
Approval by the Board of Education of an Award of Bid to, rejection of all other Bids, if any, and of an Agreement Between Owner and Contractor by and between the District and R. F. Contractors, Oakland, CA, for the latter to demolish and install new flooring in the cafeteria, teachers' staff room, and adjacent entries and hallways for the Bella Vista Elementary School Cafeteria Flooring Replacement Project, in the total amount of $175,509.95, which includes a contingency allowance of $15,000.00, as the lowest responsive, responsible bidder, with the work anticipated to commence on August 15, 2024, and required to be completed within sixty days (60), with an anticipated ending date of October 14, 2024.
|
title
Approval by the Board of Education of an Award of Bid to, rejection of all other Bids, if any, and of an Agreement Between Owner and Contractor by and between the District and R. F. Contractors, Oakland, CA, for the latter to demolish and install new flooring in the cafeteria, teachers' staff room, and adjacent entries and hallways for the Bella Vista Elementary School Cafeteria Flooring Replacement Project, in the total amount of $175,509.95, which includes a contingency allowance of $15,000.00, as the lowest responsive, responsible bidder, with the work anticipated to commence on August 15, 2024, and required to be completed within sixty days (60), with an anticipated ending date of October 14, 2024.
|