Title:
|
Approval by the Board of Education of Change Order (CO) No. 2, Agreement Between Owner and Contractor by and between the District and Asbestos Management Group, San Leandro, CA, providing the latter an extension of the term of the Agreement, from July 14, 2025, through December 31, 2025, to June 30, 2026 (an additional 181 calendar days), due to a pause for other priority site remediation by other contractor (hazardous waste cleanup due to fire) to allow for completion of the Project, as identified in the CO No. 1, for the Ralph Bunche and Hillside School Sites Demolition Projects. All other terms and conditions of the Agreement remain in full force and effect.
|