Title:
|
Approval by the Board of Education of Agreement Between Owner and Contractor by and between the District and DecoTech Systems, Inc., Walnut Creek, CA, for the latter to provide installation of 44 new cameras, 7 replacement of existing cameras, and repair of 12 cameras for the Ralph Bunche Academy at West Oakland Middle School Security Improvement Project, in the amount of $156,000.00, which includes contingency allowance totaling $12,000.00, as the lowest responsive bidder, with the work anticipated to commence on September 14, 2023, and scheduled to last for ninety days (90), with an anticipated ending of December 12, 2023.
|