Title:
|
Approval by Board of Education of Change Order No. 1 to Construction Contract with Joseph J. Albanese, Santa Clara, CA, for the latter to increase rubberized overlay from half inch to inch and a half; per RFI #12, Rip and recompact extra areas of the play yard and various other items described herein in conjunction with the Sequoia Elementary School Paving and Landscaping Project in the additional amount of $43,512.00, increasing the Agreement from $436,000.00 to $479,512.00. All other terms and conditions of the Agreement remain in full force and effect.
|