title
Approval by the Board of Education of an Agreement Between Owner and Contractor by and between the District and Native Soil, Inc., Oakland, CA, for the latter to furnish any and all labor, materials ... equipment and services for the completion of Work, as described in the Contract Documents and Bid Form 00 31 01 for schoolyard site improvement, for the Manzanita Elementary School Cal Fire Implementation Project, in the amount of $567,500.00, which includes a contingency allowance of $100,000.00, as the lowest responsive, responsible bidder, with the work anticipated to commence on May 15, 2025, and required to be completed within sixty (60) days, with an anticipated ending of July 13, 2025.