Title
Approval by the Board of Education of Change Order No.1 to Construction Contract with McGuire and Hester, Oakland, CA, for the latter to provide a credit to adjust the overall contract amount for allowance monies that were not used in conjunction with the Madison Middle School Modernization Project in the amount of ($40,386.00), decreasing the Agreement from $1,359,500.00 to $1,319,114.00. All other terms and conditions of the Agreement remain in full force and effect.