Title
Approval by the Board of Education of Change Order No. 6 to Construction Contract with Alten Construction, Richmond, CA, for the latter to provide angle at metal stud wall, extended general conditions, June 15, 2011 to July 28, 2011, 44 calendar days; extended general conditions, July 29, 2011 to August 29, 2011, 31 calendar days; fabricate interior door jamb; added crane charge in conjunction with the Elmhurst Auditorium Modernization Project in the additional amount of $130,168.00, increasing the Agreement from $4,629,953.00 to $4,760,121.00. All other terms and conditions of the Agreement remain in full force and effect.