File #: 24-2966    Version: 1 Name: Change Order No. 1, Agreement Between Owner and Contractor – Mar Con Builders, Inc. – Oakland International High School Intrusion Alarm Replacement Project - Division of Facilities Planning and Management
Type: Agreement or Contract Status: Passed
File created: 11/25/2024 In control: Deputy Chief, Facilities Planning and Management
On agenda: 1/8/2025 Final action: 1/8/2025
Enactment date: 1/8/2025 Enactment #: 24-2381
Title: Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and Mar Con Builders, Inc., Oakland, CA, for the latter's deductive Change Order charging back its remaining contingency and the amount for unused ALT (New raceway from portable to the building C & D), for the Oakland International High School Intrusion Alarm Replacement Project, in the deductive amount of $92,338.00, decreasing the Agreement price from $920,409.00 to $828,071.00. All other terms and conditions of the Agreement remain in full force and effect.
Attachments: 1. 24-2966 Change Order No. 1, Agreement Between Owner and Contractor – Mar Con Builders, Inc. – Oakland International High School Intrusion Alarm Replacement Project - Division of Facilities Planning and Management
Related files: 23-1143
Contact: Preston.Thomas@ousd.org

title

Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and Mar Con Builders, Inc., Oakland, CA, for the latter’s deductive Change Order charging back its remaining contingency and the amount for unused ALT (New raceway from portable to the building C & D), for the Oakland International High School Intrusion Alarm Replacement Project, in the deductive amount of $92,338.00, decreasing the Agreement price from $920,409.00 to $828,071.00. All other terms and conditions of the Agreement remain in full force and effect.