Title:
|
Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and Nicholas Guiterrez doing Business as N G Builder Company, Santa Clara, CA, due to rainy and/or phase out to allow students access to the yard pursuant to Early Childhood Education (ECE) guidelines, extension of the term from February 16, 2026, through May 2, 2026 to June 30, 2026 (an additional 59 calendar days), as identified in PCO No. 1, for the Harriet Tubman Child Development Center Play Yard Site Improvement Project. All other terms and conditions of the Agreement remain in full force and effect.
|