File #: 15-1108    Version: 1 Name: Project Budget Increase - Whittier (Greenleaf) Expansion - New Construction
Type: Appropriation Status: Passed
File created: 5/21/2015 In control: Operations
On agenda: 6/24/2015 Final action: 6/24/2015
Enactment date: 6/24/2015 Enactment #: 15-1071
Title: Approval by the Board of Education of Resolution 1415-1154 - Authorizing and Approving the Project Budget Increase for the Whittier (Greenleaf) Expansion - New Construction Project in the additional amount of $3,500,000.00, increasing the not to exceed amount from $6,000,000.00 to $9,500,000.00.
Attachments: 1. 15-1108 Project Budget Increase - Whittier (Greenleaf) Expansion - New Construction
Contact: Lance.Jackson@ousd.k12.ca.us
Title
Approval by the Board of Education of Resolution 1415-1154 - Authorizing and Approving the Project Budget Increase for the Whittier (Greenleaf) Expansion - New Construction Project in the additional amount of $3,500,000.00, increasing the not to exceed amount from $6,000,000.00 to $9,500,000.00.