Title:
|
Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and Asbestos Management Group, San Leandro, CA, providing for Agreement term extension from July 14, 2025 through October 11, 2025 to December 31, 2025 (81 additional calendar days), and a reduction (deduction) of the Scope of Work, as a result of an arson fire at Ralph Bunche site on August 23, 2025, decreasing the Agreement not to exceed amount by $38,000.00, from $650,000.00 to $612,000.00, for the Ralph Bunce and Hillside School Sites Demolition Projects. All other terms and conditions of the Agreement remain in full force and effect.
|