Approval by the Board of Education of Change Order No. 4 to Construction Contract with Alten Construction, Richmond, CA, for the latter to re-route plumbing vents in Rooms 219 and 307; electrical repairs to Building 200 and 300; per response to RFI #242, contractor is directed to install raceway chase through 5 HVAC doghouses in Buildings 200 and 400 for intrusion phone/data cabling in conjunction with the Montera Middle School Modernization Project in the amount of $260,562.00, increasing the Agreement from $6,640,346.00 to $6,900,908.00. All other terms and conditions of the Agreement remain in full force and effect.