Approval by the Board of Education of Change Order No. 6, Agreement Between Owner and Contractor by and between the District and Syserco Energy Solutions, Inc., Fremont, CA, providing “… a net deduction of $2,021,327.02 from the contract amount, based on the following adjustments:
Ventilation Scope Reduction (-$2,033,894.75): Deducted across 78 OUSD sites to reflect actual completed work versus initial estimates.
Additional Contingency Repairs (+$644.87): Added for the installation of additional contingency repairs (filters/A&M) at Manzanita Seed.
Second Shift Work Adjustment (+$11,922.86): Added to cover the premium/cost differential for installing CO2 sensors during second shift in active classrooms.
reducing the Agreement from $9,837,080.68 to $7,815,753.66, for the CAL Shape Design-Build Facilities Planning and Management Project. All other terms and conditions of the Agreement remain in full force and effect.
|
title Approval by the Board of Education of Change Order No. 6, Agreement Between Owner and Contractor by and between the District and Syserco Energy Solutions, Inc., Fremont, CA, providing “… a net deduction of $2,021,327.02 from the contract amount, based on the following adjustments:
1. Ventilation Scope Reduction (-$2,033,894.75): Deducted across 78 OUSD sites to reflect actual completed work versus initial estimates.
2. Additional Contingency Repairs (+$644.87): Added for the installation of additional contingency repairs (filters/A&M) at Manzanita Seed.
3. Second Shift Work Adjustment (+$11,922.86): Added to cover the premium/cost differential for installing CO2 sensors during second shift in active classrooms.
reducing the Agreement from $9,837,080.68 to $7,815,753.66, for the CAL Shape Design-Build Facilities Planning and Management Project. All other terms and conditions of the Agreement remain in full force and effect.
|