File #: 24-1476    Version: 1 Name: Change Order No. 3, Agreement Between Owner and Contractor – Mar Con Builders, Inc. – Kaiser Child Development Center Site Improvements Project – Division of Facilities Planning and Management
Type: Agreement or Contract Status: Passed
File created: 5/23/2024 In control: Deputy Chief, Facilities Planning and Management
On agenda: 6/26/2024 Final action: 6/26/2024
Enactment date: 6/26/2024 Enactment #: 24-1347
Title: Approval by the Board of Education of Change Order No. 3, Agreement Between Owner and Contractor by and between the District and Mar Con Builders, Inc., Oakland, CA, which includes PCO's 29 through 34, for additional changes that require:1? See PCO #29 for the planting of 4 new trees and installing irrigation due to CALGreen code & DSA requirements. See PCO #30 for furnishing and installing fence and gates at four locations due to safety concerns. See PCO #31 for replacing the existing sink @ unisex restroom with an ADA wall mounted lavatory sink. See PCO #32 for location description changes of the fire alarm devices due to missing signage. See PCO #33 for added fire alarm devices due to restrooms missing detection. See PCO #34 for added fire alarm devices at closets and portables B & D; for the Kaiser Child Development Center Site Improvements Project, in the additional amount of $166,038.00, increasing the not to exceed amount of the Agreement from $6,781,918.00 to $6,947,95600. All ...
Attachments: 1. 24-1476 Change Order No. 3, Agreement Between Owner and Contractor – Mar Con Builders, Inc. – Kaiser Child Development Center Site Improvements Project – Division of Facilities Planning and Management
Contact: preston.Thomas@ousd.org

title

Approval by the Board of Education of Change Order No. 3, Agreement Between Owner and Contractor by and between the District and Mar Con Builders, Inc., Oakland, CA, which includes PCO's 29 through 34, for additional changes that require:1•

See PCO #29 for the planting of 4 new trees and installing irrigation due to CALGreen code & DSA requirements.

See PCO #30 for furnishing and installing fence and gates at four locations due to safety concerns.

See PCO #31 for replacing the existing sink @ unisex restroom with an ADA wall mounted lavatory sink.

See PCO #32 for location description changes of the fire alarm devices due to missing signage. See PCO #33 for added fire alarm devices due to restrooms missing detection.

See PCO #34 for added fire alarm devices at closets and portables B & D;

for the Kaiser Child Development Center Site Improvements Project, in the additional amount of $166,038.00, increasing the not to exceed amount of the Agreement from $6,781,918.00 to $6,947,95600. All other terms and conditions of the Agreement remain in full force and effect.