Title:
|
Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and Data Sync Communications, Inc., Berkeley, CA, providing for an extension of the term of the Agreement from March 13, 2025, through June 11, 2025, to November 30, 2025 (an additional 172 calendar days), as identified in the PCO No. 1, for the Hillcrest K-8 School Security Improvement Project. All other terms and conditions of the Agreement remain in full force and effect.
|