File #: 25-0860    Version: 1 Name: Change Order No. 1, Axis Construction Consulting, Inc. - Lincoln Water Intrusion Repairs & Window Replacement Project - Division of Facilities Planning and Management
Type: Agreement or Contract Status: Board, General Consent Report
File created: 3/20/2025 In control: Deputy Chief, Facilities Planning and Management
On agenda: 4/23/2025 Final action:
Enactment date: Enactment #:
Title: Approval by the Board of Education of Change Order No. 1, Agreement for Axis Construction Consulting, Inc., Hayward, CA, by and between the District, for the former to provide additional construction services which includes PCO's 01 through 12, incorporated herein by reference as though fully set forth, for the Lincoln Water Intrusion Repairs & Window Replacement Project, in the amount of $100,000.00, increasing the contract not-to-exceed amount from $2,060,110.00 to $2,160,110.00. All other terms and conditions of the Agreement remain in full force and effect.
Attachments: 1. 25-0860 Change Order No. 1, Axis Construction Consulting, Inc. - Lincoln Water Intrusion Repairs & Window Replacement Project - Division of Facilities Planning and Management
Related files: 21-1465
Contact: preston.thomas@ousd.org
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

Approval by the Board of Education of Change Order No. 1, Agreement for Axis Construction Consulting, Inc., Hayward, CA, by and between the District, for the former to provide additional construction services which includes PCO’s 01 through 12, incorporated herein by reference as though fully set forth, for the Lincoln Water Intrusion Repairs & Window Replacement Project, in the amount of $100,000.00, increasing the contract not-to-exceed amount from $2,060,110.00 to $2,160,110.00.  All other terms and conditions of the Agreement remain in full force and effect.