Title:
|
Approval by the Board of Education of a Construction Agreement Between Owner and Contractor by and between the District and DecoTech Systems, Inc., Walnut Creek, CA, for the latter to install fiber optic cabling and integrate the network system of Lockwood STEAM Academy Main Distribution Frame and College Coliseum Preparatory Academy Main Distribution Frame for the Lockwood Network Infrastructure Project, as delineated in Exhibit A of the Agreement, in the not to exceed amount of $44,925.51, with the work scheduled to commence on October 23, 2025, and scheduled to last until December 30, 2025.
|