Title:
|
Approval by the Board of Education of the Agreement for Materials Testing and Special Inspection Services by and between the District and Consolidated Engineering Laboratories, San Ramon, CA, for the latter to provide material testing and special inspections construction services for the Garfield Elementary School Site Renovation Project, in a not-to-exceed amount of $35,865.50, which includes a contingency fee of $3,260.50 for Additional Services, with work scheduled to commence on December 12, 2024, and scheduled to last until June 30, 2025.
|