Approval by the Board of Education of Change Order No. 1 to Construction Contract with Albay Construction Co., Martinez, CA, for the latter to add ceramic tile floors in restrooms 209A, 209B, 219A and 224A; additional duct cleaning for duct not shown on drawings; perform lead abatement to resolve adhesion problems with new paint for 28 exterior doors and perform various other tasks described herein, in conjunction with the Bret Harte Middle School Modernization Project, in an additional amount of $80,071.00, increasing the Agreement from $4,169,000.00 to $4,249,071.00. All other terms and conditions of the Agreement remain in full force and effect.