Title
Approval by the Board of Education of Change Order No. 1 to Construction Contract with Alten Construction, Richmond, CA, for the latter to perform additional Scope of Work described as ASI #8.1 - electrical changes - premium time; RFI #156 - light fixture at Room 101; added step nosing at band Room 101 and various other items described herein in conjunction with the Montera Middle School Modernization Project, in the additional amount of $20,270.00, increasing the Agreement from not to exceed amount of $6,578,140.00 to $6,598,410.00. All other terms and conditions of the Agreement remain in full force and effect.