Title:
|
Ratification by State Administrator, on behalf of the District, of Change Order Nos. 2-4 to Construction Contract with G&G Builders, Pleasanton, California, for the latter to install site concrete and hand railing, connect the sewage, place temporary plywood over windows, deliver and store playground equipment, converge classroom 103 into a computer lab in conjunction with the Allendale Elementary School Relocatable Replacement Project in the amount of $67,951.91, and increasing the Agreement from $953,224.91 to $1,021,176.80 and increasing the end date from August 8, 2003 to March 30, 2004. All other terms and conditions of the Agreement remain in full force and effect.
|