Title:
|
Approval by the Board of Education of the Construction Agreement Between Owner and Contractor by and between the District and DecoTech Systems, Walnut Creek, CA., for the latter to "install 4 exterior new multi-sensor cameras outside the entry door of each building 100, 200, 400, and 500, and program them into a Milestone software system. The Contractor shall provide as-builts when work is completed, further described in the Proposal, dated September 22, 2023, and in the diagram attached as Exhibit A to this Agreement" for the Community Day School Security Improvements Project, in the not-to-exceed amount of $23,771.49, with the work scheduled to commence on January 11, 2024, and scheduled to last until March 15, 2024.
|