File #: 24-1872    Version: 1 Name: Change Order No. 1, Agreement Between Owner and Contractor - Horizon Brothers Restoration, Inc. - Oakland Technical High School Boys Gym & Portables Exterior Paint Project - Buildings and Grounds Department
Type: Agreement or Contract Status: Passed
File created: 7/23/2024 In control: Deputy Chief, Facilities Planning and Management
On agenda: 8/28/2024 Final action: 8/28/2024
Enactment date: 8/28/2024 Enactment #: 24-1524
Title: Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and Horizon Brothers Restoration, Inc., Rio Linda, CA, for the addition of the girl's gym being painted, washed, spot primed and the application of two coats of super paint in the chosen colors to the Oakland Technical High School Boys Gym & Portables Exterior Paint Project, in the amount of $57,715.00, increasing the contract price not to exceed amount from $148,800.00 to $206,515.00. All other terms and conditions of the Agreement remain in full force and effect.
Attachments: 1. 24-1872 Change Order No. 1, Agreement Between Owner and Contractor - Horizon Brothers Restoration, Inc. - Oakland Technical High School Boys Gym & Portables Exterior Paint Project - Buildings and Grounds Department
Contact: Marc.White@ousd.org

title

Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and Horizon Brothers Restoration, Inc., Rio Linda, CA, for the addition of the girl’s gym being painted, washed, spot primed and the application of two coats of super paint in the chosen colors to the Oakland Technical High School Boys Gym & Portables Exterior Paint Project, in the amount of $57,715.00, increasing the contract price not to exceed amount from $148,800.00 to $206,515.00. All other terms and conditions of the Agreement remain in full force and effect.